TEP/TEPE Surveying Field Camp Group 2: Wang-Ta-Krai

June 9, 2011 by Mr.Peerasit
- Traverse okay (precision 1/47 )
- all works have been submitted


June 6, 2011 by Mr.Peerasit
- topo-map okay
- calculation of traverse (adjust angles/azimuths)
- V = 77706m^3 (no 10% adjustment)


31 May Mr.Peerasit (only one)
- topo-map add angle and direction of angle measurement
- determination of volume - clear explanation needed
- SketchUp Okay





April 21, 2011 submitted work by Mr.Keerati (only one)
- re-submitted adjustment of all data



April 20, 2011 submitted work by Mr.Peerasit (only one)
- Configuration of housing in topo map needed check up again
- Recompute volume
- SketchUp - added bridge to complete the road
- still No Traverse / elevation correction / adjustment submitted




------------
April 11, 2011 submitted work by Mr.Peerasit (only one)

Suggestions for improvement
- Recompute volume
- Topographic map
- No Traverse / elevation correction / adjustment
- No cross check / double check
- Recheck sketchup

- Resubmit all work April 21